Development tracker

West Palm Beach development projects: downtown towers, hotels, campuses, public works and city plans

Last checked October 13, 2026. Downtown West Palm Beach development projects in the public record include two office towers under construction at CityPlace, the West Palm Point office tower, a 400-room CityPlace hotel the City Commission approved on August 31, 2026, and announced campuses for Vanderbilt University and Cleveland Clinic. Each entry below gives the location and type as its source states them, the size where a source states one, a dated status and a link to the record.

Entries whose latest record dates from 2023 to early 2025 are marked "last reported" with that date, because we could not confirm their current status. A project missing from this page is one our October 2026 research did not find in a dated public record, not one we know does not exist.

Which West Palm Beach projects are under construction?

Downtown office projects with a public record that construction has begun are listed first. Where sources disagree on height or size, both versions are shown with their dates.

West Palm Point

Location as stated: Okeechobee and Quadrille boulevards (REBusiness Online, 2023); "the corner of Okeechobee Boulevard and South Dixie Highway" (Palm Beach Post, 2025).[2][3] Type: office and retail tower. Size as stated: WPTV reported "447,484 square feet of office and retail space" when final designs were approved.[1]

Applicant named in the record: West Palm Point, which the Palm Beach Post describes as a company controlled by Charles Cohen; the Post reports city commissioners leased the land to it.[3]

Dated status: Under construction as of December 22, 2025: the developer's land-use attorney told the Post, "West Palm Point is moving along, with the cranes on site."[3] Final design approval was reported December 16, 2021.[1]

Where the sources differ: REBusiness Online (July 13, 2023) describes "a 26-story office tower"; the Palm Beach Post (December 22, 2025) describes "a 23-story office and retail complex."[2][3] On size, the Post describes "a 400,000-square-foot office tower," while WPTV reported 447,484 square feet of office and retail space in 2021; both are shown as published, and they may describe different scopes.[3][1]

Record: WPTV, December 16, 2021; REBusiness Online, July 13, 2023; Palm Beach Post, December 22, 2025

10 CityPlace and 15 CityPlace office towers

Location as stated: CityPlace, downtown West Palm Beach, as the City's annual report names them.[4] Type: Class-A office towers. Size as stated: The City's FY2025 ACFR says the two towers "will collectively contribute nearly one million square feet of premium office inventory upon completion."[4]

Dated status: The ACFR (fiscal year ended September 30, 2025) says construction commenced in March 2025. It also reports that ServiceNow announced a regional innovation hub and AI institute at 10 CityPlace, expected to deliver more than 850 high-wage jobs.[4]

Where the sources differ: The records we found do not say whether these are the same two towers the City Commission approved at The Square in January 2024 (listed below). Check the CityPlace planned development file before treating them as one project.

Record: City of West Palm Beach Finance Department, fiscal year ended September 30, 2025

Which projects have been approved?

These projects have a reported approval by the City Commission, the Downtown Action Committee or, for the hotel, an added Palm Beach County deal. An approval is not a construction start; ask for the building permit record before you assume a delivery date.

CityPlace hotel (Curio Collection by Hilton)

Location as stated: 900 S. Rosemary Ave., within the CityPlace commercial development, beside the Palm Beach County Convention Center.[6][7] Type: hotel. Size as stated: "18-story, 400-room hotel," "expected to rise 204 feet."[6]

Applicant named in the record: Related Ross.[6]

Cost or funding as stated: Palm Beach County commissioners "approved a $26 million deal" for the hotel beside the convention center.[7]

Dated status: Approved by the West Palm Beach City Commission unanimously on August 31, 2026; the county deal was reported September 29, 2026. CBS12 reports that construction remains subject to the contract.[7]

Record: CBS12, August 31, 2026; CBS12, September 29, 2026

Banyan Tree Residences West Palm Beach

Location as stated: Downtown West Palm Beach, as Stet News reports it.[8] Type: residential tower with ground-floor commercial space. Size as stated: "a 22-story, nearly 204,000-square-foot residential development with 88 condo units," with "11,000 square feet of ground floor commercial space."[8]

Applicant named in the record: Mast Capital.[8]

Dated status: Final approval reported August 14, 2026. Stet News says the project "doesn't require City Commission approval, only review from the Downtown Action Committee."[8]

Record: Stet News, August 14, 2026

The Square twin office towers (former AMC theater site)

Location as stated: Within the CityPlace Commercial Planned Development; WPTV says the towers are bound by Rosemary Avenue, Gardenia Street, Hibiscus Street and the Florida East Coast Railway tracks.[5] Type: office and retail towers. Size as stated: "744,492 square feet of office space and 63,890 square feet of retail," in two towers, "one 21 stories and one 23."[5]

Applicant named in the record: Related Cos. of New York.[5]

Dated status: Last reported January 22, 2024, when the City Commission "unanimously approved the development of two towers at the Square where the AMC theater used to be located." The developer then planned to open the buildings in September 2026; we found no later record confirming that date.[5]

Record: WPTV, January 22, 2024

Which projects are proposed or announced?

Announcements, purchase contracts and zoning requests without a recorded approval. Entries that rest on older reports show the report date.

Vanderbilt University graduate campus

Location as stated: "the 7 acres east of Tamarind Avenue from Fern to Datura streets."[9] Type: university campus.

Applicant named in the record: Vanderbilt University.[9]

Dated status: Announced, not under construction, as of January 12, 2026: Stet News reports "No shovels turned dirt Monday," and refers to "closing on the 7 acres east of Tamarind Avenue from Fern to Datura streets." It adds, "They have five to six years to develop the project."[9]

Where the sources differ: Stet News refers to "Vanderbilt University's $500 million investment"[9]; the City's FY2025 ACFR says Vanderbilt "released plans for a proposed $520 million graduate-level campus."[4]

Record: Stet News, January 12, 2026; City of West Palm Beach Finance Department, fiscal year ended September 30, 2025

Myers Auto Group site: Downtown Master Plan inclusion request

Location as stated: "915 S. Dixie Highway," a "2.5-acre site at Okeechobee Boulevard and South Dixie Highway."[11][12] Type: rezoning request for future redevelopment.

Applicant named in the record: Myers Auto Group.[11]

Dated status: Requested as of July 13, 2026, to be absorbed into the Downtown Master Plan and "the Okeechobee Boulevard zoning district, which allows 25 stories."[11] Still part of the proposal on September 8, 2026, which "would move Myers Auto Group's Jaguar dealership at 915 S. Dixie Highway into downtown zoning that allows 25 stories."[12]

Record: WLRN (Stet News), July 13, 2026; WLRN (Stet News), September 8, 2026

Cleveland Clinic hospital

Location as stated: "Australian Avenue just north of Clearwater Place" (Palm Beach Post); South Australian Avenue (City ACFR).[10][4] Type: hospital. Size as stated: "a 150-bed hospital."[10]

Applicant named in the record: Cleveland Clinic.[10]

Dated status: Last reported March 7, 2025, when the Post said Cleveland Clinic had "signed a contract to buy property" there.[10] The City's FY2025 ACFR lists it among the institutional announcements of 2025.[4] We found no construction record.

Record: Palm Beach Post, March 7, 2025; City of West Palm Beach Finance Department, fiscal year ended September 30, 2025

Transit Village

Location as stated: Clearwater Drive and South Tamarind Avenue.[10] Type: mixed-use. Size as stated: "a $1.3 billion, 6-acre mixed-use project."[10]

Dated status: Last reported March 7, 2025 (Palm Beach Post). No applicant is named in that record, and we found no later approval or permit record.[10]

Record: Palm Beach Post, March 7, 2025

Which projects are completed?

Completed work stays on the tracker with its date so the record is not lost.

NORA District, Phase 1 infrastructure

Location as stated: The NORA District, as the City's annual report names it.[4] Type: district infrastructure supporting commercial space. Size as stated: "providing 100,000 square feet of commercial space supported by Community Redevelopment Agency investment."[4]

Dated status: Completed in 2025, according to the City's ACFR for the fiscal year ended September 30, 2025.[4]

Record: City of West Palm Beach Finance Department, fiscal year ended September 30, 2025

Infrastructure in the works in West Palm Beach

Road, trail, seawall and utility work from City of West Palm Beach project pages and bid notices, Florida Department of Transportation pages and dated news reports. Each entry names the lead agency the record gives and repeats cost or funding only as stated. Several City project pages carry no publication date; those entries say so and show the date we checked them. A study or a bid notice is not a construction start.

If a property you are weighing fronts Broadway, 25th Street, Dixie Highway, Flagler Drive or Okeechobee Boulevard, read the project page for that segment and ask the City's engineering department about the construction window before you sign a lease or set a closing date.

Broadway Avenue Improvements

Location as stated: Broadway; the City says "The section of Broadway is one mile long and is in FDOT right-of-way."[13] Type: road, lighting and multiuse trail.

Lead agency: City of West Palm Beach (work in FDOT right-of-way).[13]

Dated status: Listed among the City's ongoing projects (page undated, checked October 13, 2026). The plan is to "convert Broadway to a four-lane undivided roadway with landscaping, upgraded lighting and a multiuse trail."[13]

Record: City of West Palm Beach, Engineering, page undated

25th Street Improvements Project

Location as stated: 25th Street.[14] Type: street improvements.

Lead agency: City of West Palm Beach.[14]

Cost or funding as stated: "Project value $7,032,509."[14]

Dated status: In design (page undated, checked October 13, 2026): "The project is currently in the design phase." The City says, "We anticipate construction to begin in 2026 or 2027."[14]

Record: City of West Palm Beach, Engineering, page undated

Dixie Highway (US-1) Lane Repurposing Study

Location as stated: Dixie Highway (US-1).[16] Type: road study.

Lead agency: City of West Palm Beach.[16]

Dated status: Study only (page undated, checked October 13, 2026). The recommendation is to "Reduce the road from four lanes to one lane in each direction with a center turn lane," and the City states, "This is a study, and no decisions have been made."[16]

Record: City of West Palm Beach, Engineering, page undated

Fern Street extension to Australian Avenue

Location as stated: Fern Street, across the railroad tracks toward Australian Avenue.[10] Type: road extension.

Lead agency: West Palm Beach Community Redevelopment Agency (site purchase).[10]

Cost or funding as stated: The CRA "agreed Monday to spend $5.5 million to purchase a half-acre warehouse site on Fern Street."[10]

Dated status: Last reported March 7, 2025. The City's engineering director told the Post the extension "would remove an estimated 11,000 vehicles a day from Okeechobee Boulevard and Banyan Street." We found no construction record.[10]

Record: Palm Beach Post, March 7, 2025

Flagler Drive seawall elevation

Location as stated: "a 1,425-foot segment of seawall along Flagler between Avila Road and Pershing Way."[17] Type: seawall reconstruction.

Lead agency: City of West Palm Beach.[17]

Cost or funding as stated: A "$3.63 million grant from the Florida Department of Environmental Protection."[17]

Dated status: Last reported May 19, 2023 (Palm Beach Post). We found no later dated record of construction or completion.[17]

Record: Palm Beach Post, May 19, 2023

East Central Regional Wastewater Treatment Facility Aeration Basin No. 6 Upgrades

Location as stated: The East Central Regional Wastewater Treatment Facility, as the invitation to bid names it. We have not confirmed whether the facility lies inside city limits.[18] Type: wastewater plant upgrade.

Lead agency: City of West Palm Beach (issuer of the invitation to bid).[18]

Dated status: Out to bid in 2026; the invitation set its bid deadline at 3:00 pm, March 26, 2026. We found no award record.[18]

Record: City of West Palm Beach, Procurement, 2026

Flagler Drive reroute for an expanded waterfront park (proposal)

Location as stated: Flagler Drive, downtown waterfront.[8] Type: road reroute and park expansion proposal.

Proposed by: Proposed by Ross, as Stet News reports it.[8]

Dated status: Reported August 14, 2026: "Ross' proposal to reroute Flagler Drive to expand the downtown waterfront park prompted so much community outrage." No City action approving it was found.[8]

Record: Stet News, August 14, 2026

Okeechobee Boulevard westbound repair closure

Location as stated: Okeechobee Boulevard, "the westbound lane near the intersection at Quadrille Boulevard."[19] Type: road repair.

Lead agency: Florida Department of Transportation.[19]

Dated status: Last reported July 14, 2024, as repair work by FDOT. We found no later record.[19]

Record: Hoodline, July 14, 2024

I-95 study, 6th Avenue South to Okeechobee Boulevard

Location as stated: "State Road (S.R.) 9/I-95 from 6th Avenue South" to Okeechobee Boulevard.[20] Type: highway study.

Lead agency: Florida Department of Transportation.[20]

Dated status: Paused (page undated, checked October 13, 2026): FDOT "has paused the Project Development and Environment (PD&E) Study."[20] The FDOT page places the study "in Palm Beach County, Florida"; check the page's project limits against your site.

Record: Florida Department of Transportation, page undated

Clear Lake Trail and Shoreline Enhancement

Location as stated: Clear Lake, as the City's project page names it.[15] Type: trail and shoreline enhancement.

Lead agency: City of West Palm Beach.[15]

Dated status: Completed: the City says it "has constructed the Clear Lake Trail & Shoreline Enhancement Project," which "opened to the public at the end of August 2024."[15]

Record: City of West Palm Beach, Engineering, 2024

City plans: the Comprehensive Plan, the Downtown Master Plan update and the CRA plans

Comprehensive Plan. The City states that "The City's last EAR took place in 2023," and that the resulting amendments "were then adopted in March of 2024." Florida law requires that "at least once every seven (7) years, each local government shall evaluate its Comprehensive Plan." The plan's elements are posted as PDFs, including "Element 12 - Downtown Master Plan."[21]

Housing Element. Housing is "Element 4 - Housing" of the Comprehensive Plan, posted on the same City page.[21] Our October 2026 research did not find a dated update or review status for the housing element beyond the 2024 amendments noted above.

Downtown Master Plan. The Planning Board staff report says the City "adopted its first Downtown Master Plan (DMP) in 1995 with a subsequent update occurring in 2007-2009," and that "a new DMP was adopted in 2009."[23] The City's page says "The DMP regulates approximately 767 acres" and that downtown has "more than 10.4 million square feet of nonresidential development."[22]

Downtown Master Plan update and its hearings. The City says the update has been drafted "Since February 2025" with Zyscovich Architects. Its page records a "Presentation to the Planning Board, September 15, 2026," a "DMPU Community Meeting, October 6, 2026," a Planning Board hearing on Tuesday, October 20 and a City Commission hearing on Monday, October 26.[22] The September 15, 2026 staff report proposes mixed-use incentives up to a "maximum height of 25 stories" in targeted areas and describes the Okeechobee corridor as "the traditional business district of downtown."[23]

What was dropped from the update. WLRN (Stet News) reported on September 8, 2026 that "West Palm Beach has withdrawn its proposal to allow 25-story buildings along the city's waterfront," a stretch that ran "from Datura Street to Lakeview Avenue," that "all incentives to build higher along the waterfront corridor have been removed," and that "buildings reaching up to 12 stories in the heart of the waterfront from Banyan Boulevard to Datura Street" were also scrapped. That report gave the schedule as Planning Board Sept. 15 "and then on to the City Commission Oct. 26."[12] WPTV reports, "Most of Flagler Drive will remain capped at five stories," and quotes the City's traffic engineer on Okeechobee Boulevard: "It's at about 98% capacity."[24] The Real Deal reported on July 15, 2026 that a proposed moratorium on new planned development applications in a waterfront area "would expire on January 20, 2027, unless extended by the commission."[25]

Capital Improvement Program. The City describes its CIP this way: "Updated every year, the Plan is a fiscally constrained expenditure plan" setting out "anticipated infrastructure investments over the next five years" for "streets, facilities, utilities, parks, waterfront, and transportation systems."[26] We did not retrieve the adopted CIP document itself, so no program line is listed here.

Northwood/Pleasant City CRA plan. The CRA says the district "encompasses approximately 459 acres in the northern section of West Palm Beach" and covers "Northwood Village, Pleasant City, the Broadway Corridor, the Currie Corridor, and an industrial area," with current work "advancing mixed-use opportunities within the Currie Corridor."[27] Its strategic finance plan, posted September 2, 2025, was "adopted on April 11, 2005, and is updated annually as redevelopment progresses."[28]

Consolidated Plan. The City's Housing and Community Development department says it "is developing our 2025-2029 Consolidated Plan" and held a "public meeting on Wednesday, June 25, 2025." We found no adoption record.[29]

How should you use this tracker before a lease or purchase?

Treat each entry as a pointer to the record, not as a promise of delivery. If you are a tenant comparing an existing building with a tower under construction, ask for the delivery date and the permit status in writing. If you own land near Okeechobee Boulevard, South Dixie Highway or the waterfront, read the Downtown Master Plan update as adopted after the October hearings before you price development potential.

This site's publisher is not licensed in Florida and does not represent anyone in a West Palm Beach transaction. For a lease or sale, work with a Florida-licensed broker and check the license on the Florida Department of Business and Professional Regulation license search.

If a project on this page affects a building you lease or own, send the address and the project name, and note which record you are relying on.

Ask a question about a project

Questions people ask

What new development projects are happening in downtown West Palm Beach?

Public records show 10 CityPlace and 15 CityPlace under construction since March 2025 according to the City's ACFR, West Palm Point under construction as of December 2025, a 400-room CityPlace hotel approved by the City Commission on August 31, 2026, and Banyan Tree Residences approved in August 2026. Vanderbilt and Cleveland Clinic campuses are announced but not built.

What is the 10 CityPlace office tower in West Palm Beach?

10 CityPlace is one of two Class-A office towers, with 15 CityPlace, that the City's FY2025 financial report says began construction in March 2025. The report says the pair will add nearly one million square feet of office space and that ServiceNow announced a regional innovation hub and AI institute at 10 CityPlace. For leasing status, ask a Florida-licensed broker.

How tall is West Palm Point?

The sources disagree. REBusiness Online described a 26-story office tower in July 2023, and the Palm Beach Post described a 23-story office and retail complex in December 2025. WPTV reported 447,484 square feet of office and retail space when final designs were approved in December 2021. Check the City's current approval for the figure that governs.

When is the Downtown Master Plan update hearing?

The City's Downtown Master Plan page lists a Planning Board hearing on Tuesday, October 20 and a City Commission hearing on Monday, October 26. A Planning Board presentation took place on September 15, 2026 and a community meeting on October 6, 2026. WLRN reported the 25-story waterfront proposal was withdrawn before those hearings.

Is Vanderbilt building a campus in West Palm Beach?

Vanderbilt has announced one, but as of January 12, 2026 Stet News reported no construction had started, and it referred to closing on the 7 acres east of Tamarind Avenue. Stet News describes a $500 million investment; the City's FY2025 ACFR describes a proposed $520 million graduate-level campus. Check for a later permit record.

Sources

  1. Final design approved for West Palm Point project, WPTV, December 16, 2021. Accessed October 13, 2026.
  2. CRBC to break ground on office tower and parking garage in downtown West Palm Beach, REBusiness Online, July 13, 2023. Accessed October 13, 2026.
  3. West Palm tent foreclosure dismissed (Palm Beach Post, via Yahoo News), Palm Beach Post, December 22, 2025. Accessed October 13, 2026.
  4. Annual Comprehensive Financial Report (hosted by the Florida Auditor General), City of West Palm Beach Finance Department, fiscal year ended September 30, 2025. Accessed October 13, 2026.
  5. West Palm Beach City Commission approves twin towers at The Square, WPTV, January 22, 2024. Accessed October 13, 2026.
  6. City Commission backs CityPlace hotel on Rosemary Avenue, CBS12, August 31, 2026. Accessed October 13, 2026.
  7. Palm Beach County bets on bigger conventions with Related Ross deal, CBS12, September 29, 2026. Accessed October 13, 2026.
  8. Another tower rising in downtown West Palm Beach, Stet News, August 14, 2026. Accessed October 13, 2026.
  9. Vanderbilt commits to West Palm, Stet News, January 12, 2026. Accessed October 13, 2026.
  10. Clear Lake district booms in West Palm Beach (Palm Beach Post, via Yahoo News), Palm Beach Post, March 7, 2025. Accessed October 13, 2026.
  11. Luxury car dealer zooms into West Palm Beach development race, WLRN (Stet News), July 13, 2026. Accessed October 13, 2026.
  12. High-rise waterfront buildings axed from West Palm's downtown proposal, WLRN (Stet News), September 8, 2026. Accessed October 13, 2026.
  13. Broadway Avenue Improvements, City of West Palm Beach, Engineering, page undated. Accessed October 13, 2026.
  14. 25th Street Improvements Project, City of West Palm Beach, Engineering, page undated. Accessed October 13, 2026.
  15. Clear Lake Trail Project, City of West Palm Beach, Engineering, 2024. Accessed October 13, 2026.
  16. Dixie Highway Lane Repurposing Study, City of West Palm Beach, Engineering, page undated. Accessed October 13, 2026.
  17. West Palm Beach updates Flagler Drive seawall plans (Palm Beach Post, via Yahoo News), Palm Beach Post, May 19, 2023. Accessed October 13, 2026.
  18. Invitation to bid, ECR WWTF Aeration Basin No. 6 Upgrades, City of West Palm Beach, Procurement, 2026. Accessed October 13, 2026.
  19. Okeechobee Blvd closure in West Palm Beach for FDOT repair work, Hoodline, July 14, 2024. Accessed October 13, 2026.
  20. I-95 from 6th Avenue South to Okeechobee Boulevard PD&E Study, Florida Department of Transportation, page undated. Accessed October 13, 2026.
  21. Comprehensive Plan (What are my property's setbacks?), City of West Palm Beach, page undated. Accessed October 13, 2026.
  22. Downtown Master Plan, City of West Palm Beach, Planning Division, page undated. Accessed October 13, 2026.
  23. Downtown Master Plan Update, Planning Board staff report, City of West Palm Beach Planning Board, September 15, 2026. Accessed October 13, 2026.
  24. Downtown master plan moves forward after changes remove 25-story waterfront buildings, WPTV, September 2026. Accessed October 13, 2026.
  25. West Palm Beach development moratorium heads to final vote, The Real Deal, July 15, 2026. Accessed October 13, 2026.
  26. Capital Improvement Program (CIP), City of West Palm Beach, Engineering, page undated. Accessed October 13, 2026.
  27. Northwood/Pleasant City district page, West Palm Beach Community Redevelopment Agency, page undated. Accessed October 13, 2026.
  28. Northwood/Pleasant City CRA strategic finance plan (Exhibit A), West Palm Beach Community Redevelopment Agency, September 2, 2025. Accessed October 13, 2026.
  29. Consolidated Plan, City of West Palm Beach, Housing and Community Development, page undated. Accessed October 13, 2026.